In Paris, works that change a building’s external appearance, such as replacing windows or renovating a shopfront, generally require a prior declaration of works (déclaration préalable) filed with the town hall (mairie), whereas purely interior works are usually exempt. A shop sign and premises open to the public involve procedures of their own, and the co-ownership’s approval remains separate. This guide sets out the rules published on official websites and shows where to confirm them for your address.
Which procedure for which works?
This table gives the most likely procedure. Only the competent authority can confirm it for a given property.
| Works | Likely procedure | Where to check |
|---|---|---|
| Interior fit-out | Generally no planning formality | Town hall, and the PSMV in a conservation area |
| Windows, external joinery | Prior declaration (déclaration préalable) | Town hall |
| Shopfront, without change of use | Prior declaration (déclaration préalable) | Town hall |
| Shopfront, with change of use | Building permit (permis de construire) | Town hall |
| Facade cleaning and restoration (ravalement) | Prior declaration in the cases provided for | Town hall |
| Shop sign | Prior authorisation | Town hall (in Paris, a dedicated online service) |
| Premises open to the public | Works authorisation (autorisation de travaux) | Town hall |
| Common parts, building’s appearance | Vote of the general meeting of co-owners | Syndic, co-ownership rules |
Do interior works need an authorisation?
As a general rule, no. The French Planning Code (code de l’urbanisme) exempts works carried out on an existing building from any formality, except those it lists (article R. 421-13). These exceptions include a change of use (changement de destination) of premises, for example from a shop to a dwelling, and turning more than 5 m² of enclosed, covered space into floor area (surface de plancher).
In an area covered by a conservation and enhancement plan (plan de sauvegarde et de mise en valeur, PSMV), interior works may also be concerned: those affecting architectural or decorative features protected by that plan (article R. 421-17).
When is a prior declaration required?
A prior declaration is required for works that change the external appearance of an existing building (article R. 421-17 of the Planning Code). Replacing windows or external joinery, altering a shopfront or changing shutters all fall into this category. The Ville de Paris states that any change to the external appearance must be covered by a planning authorisation, including for like-for-like works.
Facade cleaning and restoration (ravalement) follows a separate rule. It is exempt from prior declaration, except in the cases set by article R. 421-17-1: notably in a site patrimonial remarquable (a protected heritage area), near a historic monument, or in a municipality that has imposed it by council decision. In Paris, check before any ravalement.
For a ground-floor shop, the Ville de Paris indicates that changing the frontage without a change of use requires a prior declaration. If it comes with a change of use, a building permit (permis de construire) is needed. Paris applications are made online, through the “Démarches d’urbanisme” (planning procedures) online service.
What changes in a protected area?
Paris has two sites patrimoniaux remarquables: the Marais and most of the 7th arrondissement. They are governed by a conservation and enhancement plan (PSMV), not by the bioclimatic local urban plan (Plan local d’urbanisme bioclimatique, PLU) that applies to the rest of the city. That plan was approved by the Conseil de Paris (city council) on 20 November 2024. In these two areas, planning authorisations are subject to the agreement of the architecte des Bâtiments de France (ABF), the state architect responsible for protected heritage.
The ABF also steps in near historic monuments. Works likely to change the external appearance of a building protected as part of a monument’s surroundings (abords) require their agreement. This applies throughout the defined surroundings perimeter or, where no perimeter has been defined, within the monument’s line of sight and less than 500 m from it. This rule also applies in the inner suburbs (petite couronne), where the applicable planning rules can be consulted with the municipality.
Does a shop sign need an authorisation?
Yes, in Paris. The French Environment Code (code de l’environnement) makes installing a sign subject to authorisation where a local advertising regulation (règlement local de publicité) applies (article L. 581-18), and Paris applies its own. The City requires an authorisation to install, alter or replace a sign, with one application per sign panel when a shop is renovated.
Since 1 October 2025, these applications have been made exclusively online, through the “Terrasses, étalages, enseignes” (terraces, displays, signs) online service. This authorisation comes on top of the prior declaration when the shopfront is altered.
What procedures apply to premises open to the public?
A shop open to customers is an establishment open to the public (établissement recevant du public, ERP). Works that create, fit out or alter an ERP may only be carried out after an authorisation that checks compliance with accessibility and fire-safety rules (article L. 122-3 of the French Construction and Housing Code, code de la construction et de l’habitation).
The application is filed with the town hall. It accompanies the prior declaration or building permit when these are required, and may be necessary even for works exempt from planning authorisation. This article was amended by a law of 26 May 2026: have the procedure that applies to your premises confirmed.
Is the co-ownership’s approval enough?
No. In a co-owned building (copropriété), works that change the building’s external appearance, such as replacing windows, or that affect the common parts require the authorisation of the general meeting of co-owners (assemblée générale) before any work begins. This vote does not replace the planning authorisation, and a planning authorisation does not replace this vote.
How long does the review take?
For a prior declaration, the review period is generally one month from filing with the town hall. It is generally extended to two months in a protected area, notably in a site patrimonial remarquable or near a historic monument; the town hall informs the applicant within a month of filing. In Paris, the statutory period for a permanent sign application is two months.
Take these periods into account before setting the start date of the works concerned.
Can you handle the authorisations?
We do not file authorisation applications. When we study your project, we check with you which ones your works may require: a general meeting vote, a prior declaration or building permit, the ABF’s agreement, a sign, premises open to the public. Filing remains your responsibility or that of your architect.
For windows, entrance doors and shopfronts, explore our exterior works. For a specific project, tell us about it.
What to check before signing
- Is the address in a site patrimonial remarquable or near a historic monument?
- Do the works change the external appearance, the use of the premises or their floor area?
- Is a sign being installed, altered or replaced?
- Are the premises open to the public?
- Does the general meeting of co-owners need to vote?
- Who files each application, and when is the decision expected?
- Does the quote identify the works that depend on an authorisation?
Official sources (in French)
- Service Public: prior declaration of works.
- Légifrance: Planning Code, article R. 421-13.
- Légifrance: Planning Code, article R. 421-17.
- Légifrance: Planning Code, article R. 421-17-1.
- Ville de Paris: frequently asked questions on planning.
- Ville de Paris: bioclimatic local urban plan.
- Ville de Paris: protected heritage areas and PSMV.
- Ministère de la Culture: works near a historic monument.
- Ville de Paris: signs and advertising.
- Légifrance: Environment Code, article L. 581-18.
- Légifrance: Construction and Housing Code, article L. 122-3.
- Entreprendre Service Public: accessibility of an ERP.
- Service Public: works in a co-owned building.
Verified on 4 October 2026.